Summary
The Supreme Court of Montana reviewed a dispute arising from a condominium construction contract, including payment withholding, delay penalties, punch-list and warranty work, construction-lien recovery, prejudgment interest, overhead costs, and attorney fees. The court held that the owner's failure to pay the architect-certified amount materially breached the contract, relieving the contractor of further performance obligations and requiring reversal of related offsets. The court also awarded prejudgment interest on specified, ascertainable amounts and otherwise affirmed in part and reversed and remanded in part.
Holdings
- P&D's failure to pay the amount certified by the architect constituted a material breach of the contract, and Talcott was entitled to stop work after giving the contractually required notice. That breach relieved Talcott of its remaining performance obligation, including punch-list and warranty work; therefore, P&D could not recover the $12,807.33 it spent performing that work.
- Talcott was entitled to prejudgment interest from July 15, 1992, the date it filed the construction lien, on the certain or calculable amounts wrongfully withheld, including the delay penalty, repainting amount, anticipated warranty amount, and approved changes.
- When an appellate court increases a money judgment by an amount that was sought by the prevailing party but wrongfully denied below and that amount was discreetly identifiable, the increase bears post-judgment interest from the date of the lower court's judgment, rather than only from the date of the new judgment on remand.
- Talcott was not entitled to additional home-office overhead because the evidence was insufficient to establish entitlement or a specific amount by a preponderance of the evidence.
- The District Court abused its discretion by basing Talcott's attorney-fee award on an affidavit submitted nineteen months after the evidentiary hearing, because Talcott had no opportunity to hear testimony or cross-examine the affiant. The fee award had to be reversed and remanded for a hearing at which both parties could present evidence and conduct cross-examination.
Questions Presented
- Whether Talcott remained contractually obligated to perform punch-list and warranty work after P&D failed to pay the amount certified by the architect.
- Whether Talcott was entitled to prejudgment interest on amounts recoverable under its construction lien.
- Whether Talcott was entitled to additional home-office overhead resulting from delays attributed to P&D.
- Whether the District Court abused its discretion in determining Talcott's attorney-fee award.
Disposition
reversed_and_remanded
Cases Cited (18)
- Fiedler v. Fiedler, 266 Mont. 133, 879 P.2d 675 (1994)(followed)
- Somont Oil Co. v. A & G Drilling, Inc., 2006 MT 90, 332 Mont. 56, 137 P.3d 536(followed)
- American Music Co. v. Higbee, 2004 MT 349, 324 Mont. 348, 103 P.3d 518(followed)
- King Resources, Inc. v. Oliver, 2002 MT 301, 313 Mont. 17, 59 P.3d 1172(followed)
- Western Media, Inc. v. Merrick, 232 Mont. 480, 757 P.2d 1308 (1988)(followed)
- Rossi v. Pawiroredjo, 2004 MT 39, 320 Mont. 63, 85 P.3d 776(followed)
- DeVoe v. Gust. Lagerquist & Sons, Inc., 244 Mont. 141, 796 P.2d 579 (1990)(followed)
- Ramsey v. Yellowstone Neurosurgical Assocs., 2005 MT 317, 329 Mont. 489, 125 P.3d 1091(followed)
- Price Bldg. Service, Inc. v. Holms, 214 Mont. 456, 693 P.2d 553 (1985)(followed)
- Safeco Ins. Co. v. Lovely Agency, 215 Mont. 420, 697 P.2d 1354 (1985)(followed)
Showing top 10 of 18.
Cited In (0)
No citing cases on record yet.