Truss Works, Inc. v. Oswood Construction Company

Truss Works, Inc. v. Oswood Construction Co., 2022 MT 42 · Supreme Court of the State of Montana · March 1, 2022 · No. DA 21-0185

Summary

The Montana Supreme Court affirmed a District Court judgment awarding Truss Works, Inc. unpaid contract amounts and attorney fees in an action to foreclose a construction lien. The Court held that the District Court's express and implied findings sufficiently addressed Oswood Construction Company's counterclaim for delay damages and were supported by substantial evidence. The Court also concluded that Oswood's nonpayment constituted an incidental breach and that the evidence supported findings concerning responsibility for project delays and truss-hanger obligations.

Holdings

  1. The District Court's express and implied findings were sufficient to permit informed appellate review and implicitly rejected Oswood's counterclaim by finding that Oswood was more responsible for the project delays.
  2. The District Court did not clearly err in finding that Oswood failed to cooperate reasonably during the submittal process and was largely responsible for the resulting delays.
  3. Oswood's failure to pay the final installment and contract balance was an incidental breach, not a material breach, because it concerned only part of the consideration and did not justify rescission.
  4. The omission of an express finding on responsibility for the hangers did not warrant reversal because the District Court's implied finding that Truss Works was not required to supply them was supported by the evidence and was not necessary to disturb the judgment.

Questions Presented

  1. Whether the District Court made sufficient findings of fact and conclusions of law to support judgment for Truss Works despite not expressly ruling on Oswood's counterclaim.
  2. Whether the District Court clearly erred in finding that Oswood was largely responsible for delays in the truss-submittal process.
  3. Whether the District Court's finding that Oswood 'fully breached' the contract constituted an erroneous finding of material breach.
  4. Whether the District Court's implied findings adequately resolved the parties' dispute over responsibility for designing and supplying truss hangers.

Disposition

affirmed

Cases Cited (6)

  • Norwood v. Service Distrib., Inc., 2000 MT 4, ¶¶ 21-22, 29, 297 Mont. 473, 994 P.2d 25(followed)
  • State v. Baty, 2017 MT 89, ¶¶ 11, 13, 387 Mont. 252, 393 P.3d 187(followed)
  • Snavely v. St. John, 2006 MT 175, ¶ 11, 333 Mont. 16, 140 P.3d 492(followed)
  • Nicholson v. United Pacific Insurance Company, 219 Mont. 32, 710 P.2d 1342 (1984)(distinguished)
  • State v. Wetzel, 2005 MT 154, ¶ 11, 327 Mont. 413, 114 P.3d 269(followed)
  • Brunette v. State, 2016 MT 128, ¶ 36, 383 Mont. 458, 372 P.3d 476(followed)

Cited In (0)

No citing cases on record yet.

Court Document

Open PDF
Loading document…