Summary
The New York Appellate Division considers the State’s motion for summary judgment concerning claims by a construction contractor for compensation for extra work on a Department of Transportation project. The court held that the contractor’s failure to comply with contractual notice and reporting requirements defeated its claims for extra traffic-control and survey work, but triable issues remained regarding bridge construction costs and quantity underruns. The court also upheld the denial of summary judgment on the contractor’s claim for interest based on allegedly untimely final payment and dismissed the contractor’s cross appeal.
Holdings
- Contract provisions requiring prompt notice and documentation of claims for additional compensation are conditions precedent to suit or recovery, and express conditions must be literally performed; substantial performance is insufficient. Strict noncompliance generally waives the claim for additional compensation.
- The State was entitled to summary judgment dismissing the third and fourth causes of action because Rifenburg failed to comply with the contract's notice and reporting requirements and did not raise a triable issue of fact.
- Summary judgment was properly denied on the first cause of action because, although the State established an untimely claim under the contractual notice provisions, Rifenburg submitted evidence creating a factual issue concerning the Department of Transportation's knowledge of design errors and indications that Rifenburg would be compensated.
- Summary judgment was properly denied on the second cause of action because Rifenburg raised triable issues of fact as to whether it knew or should have known of the quantity underruns in light of numerous project additions and deletions.
- The State was not entitled to summary judgment dismissing the seventh cause of action for interest under State Finance Law § 179-f because the 18-month period between acceptance of the work and written notice of missing documentation was not excluded when calculating the timeliness of final payment.
- Rifenburg's cross appeal was dismissed because Rifenburg was not aggrieved by the order denying the State's motion.
Questions Presented
- Whether the State was entitled to summary judgment dismissing claims for extra traffic-control and survey work because Rifenburg failed to comply strictly with contractual notice and reporting requirements.
- Whether triable issues of fact precluded summary judgment on Rifenburg's claim for additional bridge-construction costs allegedly caused by Department of Transportation design errors despite an untimely notice.
- Whether triable issues of fact existed regarding Rifenburg's knowledge of quantity underruns and changes that allegedly supported a claim for additional compensation.
- Whether the State was entitled to summary judgment dismissing the claim for interest under State Finance Law § 179-f based on the asserted timeliness of its final payment.
- Whether Rifenburg's cross appeal had to be dismissed because Rifenburg was not aggrieved by the order.
Disposition
other
Cases Cited (9)
- A.H.A. Gen. Constr. v. New York City Hous. Auth., 92 N.Y.2d 20, 30-31, 33-34 (1998), rearg. denied, 92 N.Y.2d 920 (1998)(followed)
- Sicoli & Massaro v. Niagara Falls Hous. Auth., 281 A.D.2d 966 (2001)(followed)
- Tug Hill Constr. v. County of Broome, 270 A.D.2d 755, 756 (2000)(followed)
- MHR Capital Partners LP v. Presstek, Inc., 12 N.Y.3d 640, 645 (2009)(followed)
- Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co., 86 N.Y.2d 685, 690 (1995)(followed)
- Fahs Rolston Paving Corp. v. County of Chemung, 43 A.D.3d 1192, 1194 (2007)(followed)
- Bat-Jac Contr. v. New York City Hous. Auth., 1 A.D.3d 128 (2003)(followed)
- Zuckerman v. City of New York, 49 N.Y.2d 557, 562 (1980)(followed)
- Weichert v. Shea, 186 A.D.2d 992 (1992)(followed)
Cited In (0)
No citing cases on record yet.