Summary
The Supreme Court of North Dakota affirmed the dismissal of Baukol Builders' challenge to Grand Forks County's award of a public construction contract to a higher-dollar bidder. The court held that the completion date was a stated bidding criterion and that the applicable competitive-bidding statutes permitted the County to consider factors beyond the lowest dollar bid. The court also upheld the denial of Baukol Builders' post-trial motions and request for attorney fees.
Holdings
- A bidder that submitted a timely bid and was not shown to have been harmed by the early opening of bids could not challenge the County's failure to comply with the statutory twenty-one-day publication period.
- The County did not use unstated or unwritten criteria because the bid documents expressly required bidders to state their proposed completion dates, making completion time a stated item of competition; consideration of the resulting revenue and interest implications was necessarily related to that stated criterion.
- N.D.C.C. §§ 48-01.1-02 and 48-01.1-07, construed together, authorized a public entity to exercise some discretion in awarding a contract to the lowest responsible and lowest and best bidder; they did not require selection of the lowest dollar bidder.
- The County did not abuse its discretion or act arbitrarily, unreasonably, or capriciously in awarding the contract to Construction Engineers.
- The district court did not abuse its discretion in denying the motions for a new trial and renewed post-trial relief based on allegedly newly discovered evidence.
- Baukol Builders was not entitled to attorney fees under N.D.C.C. § 28-26-31 or Chambers v. NASCO, Inc., because the County acted in good faith and there was no qualifying bad-faith conduct.
Questions Presented
- Whether Baukol Builders was barred from challenging the County's failure to publish the bid notice at least twenty-one days before opening bids after submitting a timely bid.
- Whether the County used unstated or unwritten criteria by considering proposed completion dates, anticipated prisoner-housing revenue, and interest savings in awarding the contract.
- Whether N.D.C.C. §§ 48-01.1-02 and 48-01.1-07 authorized the County to exercise discretion in selecting the lowest responsible and lowest and best bidder rather than the lowest dollar bidder.
- Whether the County abused its discretion or acted arbitrarily, unreasonably, capriciously, fraudulently, or collusively in awarding the contract to Construction Engineers.
- Whether the district court abused its discretion by denying Baukol Builders' post-trial motions based on allegedly newly discovered evidence.
- Whether Baukol Builders was entitled to attorney fees under N.D.C.C. § 28-26-31 or the inherent-power doctrine recognized in Chambers v. NASCO, Inc.
Disposition
affirmed
Cases Cited (16)
- Quist v. Best W. Int'l, Inc., 354 N.W.2d 656, 664-65 (N.D. 1984)(followed)
- Frieh v. City of Edgeley, 317 N.W.2d 818, 819-20 (N.D. 1982)(followed)
- Mini Mart, Inc. v. City of Minot, 347 N.W.2d 131, 133, 141 (N.D. 1984)(distinguished)
- Danzl v. City of Bismarck, 451 N.W.2d 127, 128, 130-32 (N.D. 1990)(distinguished)
- Becker Elec., Inc. v. City of Bismarck, 469 N.W.2d 159, 162 (N.D. 1991)(followed)
- In re P.F., 2008 ND 37, ¶ 11, 744 N.W.2d 724(followed)
- Estate of Elken, 2007 ND 107, ¶ 7, 735 N.W.2d 842(followed)
- Chaffee v. Crowley, 49 N.D. 111, 114, 190 N.W. 308 (1922)(followed)
- Ellingson v. Cherry Lake Sch. Dist., 55 N.D. 141, 148-49, 212 N.W. 773, 775-76 (1927)(followed)
- Roe v. Doe, 2002 ND 136, ¶ 12, 649 N.W.2d 566(followed)
Showing top 10 of 16.
Cited In (0)
No citing cases on record yet.
Court Document
Open PDFLoading document…