Industrial Power Systems, Inc. v. Kraft Heinz Food Co. LLC

Case No. 3:22-cv-01703 · United States District Court for the Northern District of Ohio, Western Division · February 13, 2026 · No. 3:22-cv-01703

Summary

In this bench-trial memorandum opinion, the Northern District of Ohio addresses construction-project delays, change orders, breach-of-contract claims, mechanic’s-lien validity, quiet title, slander of title, indemnification, and delay damages. The court concluded that Kraft Heinz failed to prove a material breach by Industrial Power Systems or invalidate its mechanic’s lien, while IPS established liability on its delay claim; the opinion indicates that damages remained for determination.

Holdings

  1. Kraft failed to prove that IPS materially breached the contract. Project delay, without more, did not establish material nonperformance where the evidence showed continued performance, substantial compliance, and delays associated with design problems, owner directives, changes, and other project conditions.
  2. Kraft was not entitled to liquidated damages because the court found no material breach by IPS and the record reflected responsibility for delay on both sides.
  3. Kraft failed to prove that IPS's mechanic's lien was invalid because of either the property-description discrepancy or the timing of recording. The lien was timely and its detailed legal description sufficiently identified the property.
  4. Kraft's quiet-title and slander-of-title claims failed. The lien was not shown to be an invalid cloud on title, and Kraft did not prove the falsity, malice or reckless disregard, and special-damages elements required for slander of title.
  5. Kraft could not recover contractual indemnification on the liability record because it failed to prove a triggering breach, and its proposed construction of the indemnity clause would be unenforceable to the extent it shifted liability for Kraft's own negligence.
  6. IPS established liability on its delay-related breach-of-contract theory. Owner-driven and design-related problems, later changes, and resulting critical-path, sequencing, rework, and productivity impacts caused compensable delay, subject to determination of damages in a later phase.
  7. IPS satisfied the notice element of its delay claim through actual and, at minimum, constructive notice. Kraft received contemporaneous communications, meeting and change-order information, and formal claim submissions identifying the delay and cost impacts.
  8. IPS could not recover under unjust enrichment because the express Construction Services Agreement and purchase orders governed the parties' relationship and supplied the measure of compensation for the dispute.
  9. The lien-foreclosure claim could not be resolved at the liability phase and was dismissed without prejudice to renewal in an appropriate procedural posture consistent with Ohio foreclosure requirements and the eventual damages determination.

Questions Presented

  1. Whether IPS materially breached the construction contracts by failing to meet project schedules or by its construction management, sequencing, and pacing.
  2. Whether Kraft was entitled to liquidated damages based on project delay.
  3. Whether IPS's mechanic's lien was invalid because of the property description or the timing of its recording.
  4. Whether Kraft's quiet-title and slander-of-title claims based on the mechanic's lien could succeed.
  5. Whether Kraft could enforce contractual indemnification against IPS for losses arising from IPS's alleged breach or lien-related conduct.
  6. Whether IPS established entitlement and causation on its delay-related breach-of-contract claim.
  7. Whether IPS provided sufficient actual or constructive notice of its delay claim under the contractual notice requirements.
  8. Whether IPS could recover under unjust enrichment despite the express contractual framework governing the parties' relationship.
  9. Whether IPS's lien-foreclosure claim could be resolved during the liability phase.

Disposition

other

Cases Cited (21)

  • Price v. KNL Custom Homes, Inc., 2015-Ohio-436, ¶ 32 (Ohio Ct. App. 2015)(followed)
  • Marion Family YMCA v. Hensel, 178 Ohio App. 3d 140, 142-143 (Ohio Ct. App. 2008)(followed)
  • Crockett Homes, Inc. v. Tracy, 2024-Ohio-1464, ¶ 125 (Ohio Ct. App. 2024)(followed)
  • Thompson v. Executive Transportation Service, 2004 WL 291188, at *3 (Ohio Ct. App. 2004)(followed)
  • Dugan & Meyers Construction Co. v. Ohio Department of Administrative Services, 113 Ohio St. 3d 226, 230, 232 (Ohio 2007)(followed)
  • Merritt v. Anderson, 2009 WL 975749, at *3-*5 (Ohio Ct. App. 2009)(followed)
  • Applied Contracting Corp. v. Ohio Department of Transportation, 2011 WL 4947364, ¶ 108 (Ohio Ct. Cl. 2011)(followed)
  • Turzillo Contracting Co. v. Messer & Sons, Inc., 23 Ohio App. 2d 179, 184 (Ohio Ct. App. 1969)(followed)
  • Buckeye State Hauling, Inc. v. Troy, 1974 WL 184519, at *2 (Ohio Ct. App. 1974)(followed)
  • Guernsey Bank v. Milano Sports Enterprises, 2008-Ohio-2420, ¶ 42 (Ohio Ct. App. 2008)(followed)

Showing top 10 of 21.

Cited In (0)

No citing cases on record yet.

Court Document

Open PDF
Loading document…