Pace Construction Services LLC v. Federal Insurance Co.

Pace Construction · United States District Court for the Western District of Louisiana, Lake Charles Division · January 13, 2026 · No. 2:23-CV-00197

Summary

The United States District Court for the Western District of Louisiana ruled on Sauer Construction LLC’s Rule 12(b)(6) motion to dismiss Pace Construction Services LLC’s counterclaims. The court held that Pace failed to adequately plead a bad-faith breach of contract or entitlement to consequential damages, while allowing its claim for the unpaid subcontract balance to proceed. The challenged counterclaims were dismissed without prejudice, with 60 days allowed for amendment; the ruling was signed on January 13, 2026.

Holdings

  1. The subcontract's provision making a time extension the subcontractor's sole remedy for delay is enforceable absent evidence of intentional or gross fault, but it does not bar a claim to the extent the alleged damages resulted from delays or hindrances created by Sauer and the claimant adequately invokes the gross-fault exception.
  2. Pace failed to state a claim for bad-faith breach of contract because it alleged an underlying breach but did not allege facts showing that the breach itself was motivated by an intent to harm or by a dishonest or morally questionable motive.
  3. Because Pace failed to plausibly plead a bad-faith breach, its claim for consequential damages based on that theory also failed.
  4. Federal Rule of Civil Procedure 8 does not require a claimant to identify contractual provisions with exhaustive granularity, although identifying specific provisions is preferable when possible.

Questions Presented

  1. Whether the subcontract's no-damages-for-delay provision barred Pace's claims for delay-related and consequential damages at the pleading stage.
  2. Whether Pace plausibly alleged a bad-faith or intentional breach of contract sufficient to invoke the gross-fault exception to the contractual limitation of liability under Louisiana law.
  3. Whether Pace adequately identified an underlying contractual breach under Federal Rule of Civil Procedure 8.

Disposition

other

Cases Cited (14)

  • Wilson v. Birnberg, 667 F.3d 591, 595 (5th Cir. 2012)(followed)
  • Collins v. Morgan Stanley Dean Witter, 224 F.3d 496, 498-99 (5th Cir. 2000)(followed)
  • Hall v. Hodgkins, 305 Fed. App'x 224, 227 (5th Cir. 2008) (unpublished)(followed)
  • Bustos v. Martini Club, Inc., 599 F.3d 458, 461 (5th Cir. 2010)(followed)
  • In re Katrina Canal Breaches Litigation, 495 F.3d 191, 205 (5th Cir. 2007)(followed)
  • Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)(followed)
  • Lone Star Fund V (U.S.), L.P. v. Barclays Bank PLC, 594 F.3d 383, 387 (5th Cir. 2010)(followed)
  • Alonso v. Westcoast Corp., 920 F.3d 878, 884-85 (5th Cir. 2019)(applied)
  • Wadick v. Gen. Heating & Air Conditioning, LLC, 145 So. 3d 586, 599 (La. Ct. App. 4th Cir. 2014)(followed)
  • Pellerin Const., Inc. v. Witco Corp., 169 F. Supp. 2d 568, 584-85 (E.D. La. 2001)(followed)

Showing top 10 of 14.

Cited In (0)

No citing cases on record yet.

Court Document

Open PDF
Loading document…