Summary
The Supreme Court of Virginia reviewed consolidated appeals challenging the State Corporation Commission’s approval of certificates of public convenience and necessity for VEPCO’s Aspen-Golden and Apollo-Twin Creeks transmission projects in Loudoun County. The appellants primarily argued that a portion of the Aspen-Golden transmission lines should be constructed underground and that the Commission failed to properly verify reliability data and consider statutory, scenic, historic, environmental, and comprehensive-plan concerns. The Court held that the Commission adequately verified the supporting information and reasonably determined that overhead construction was the feasible option, affirming the Commission’s judgments.
Holdings
- The Commission satisfied Code § 56-46.1(B) by verifying the load-flow modeling, contingency analyses, and reliability needs supporting the Aspen-Golden Project and its proposed overhead installation method.
- The Commission reasonably considered and rejected underground construction of a portion of the Aspen-Golden transmission lines because of increased cost, engineering challenges, analytical deficiencies, and impediments to timely completion.
- The Commission adequately considered the Aspen-Golden Project's effects on the Belmont Scenic Viewshed Easement and reasonably determined that Route 1AA was the optimal route after weighing those effects with other statutory factors.
- Code § 56-46.1(A) required the Commission to receive and give consideration to Loudoun County's comprehensive plan, but did not require a separate substantial-accord determination under Code § 15.2-2232.
- The Commission reasonably determined that Route 1AA avoided or reasonably minimized adverse impacts to scenic assets, historic and cultural resources, and the environment to the greatest extent reasonably practicable.
- The Commission did not abuse its discretion by declining to impose additional conditions addressing the visual impacts of the Aspen-Golden Project.
- The Commission did not err by approving the Apollo-Twin Creeks Project without provisions accommodating underground construction of the Aspen-Golden transmission lines.
Questions Presented
- Whether the Commission adequately verified the load-flow modeling, contingency analyses, and reliability needs supporting the Aspen-Golden Project and its proposed overhead installation method.
- Whether the Commission reasonably rejected underground construction of a portion of the Aspen-Golden transmission lines based on cost, engineering challenges, analytical deficiencies, and potential impediments to timely construction.
- Whether the Commission adequately considered the Belmont Scenic Viewshed Easement in selecting the Aspen-Golden route.
- Whether the Commission was required to determine that the Aspen-Golden transmission lines were in substantial accord with Loudoun County's comprehensive plan under Code § 15.2-2232.
- Whether the Commission adequately determined that the selected route would avoid or reasonably minimize adverse impacts to scenic, historic, cultural, and environmental resources.
- Whether the Commission abused its discretion by declining to impose additional conditions proposed by Lansdowne Conservancy.
- Whether approval of the Apollo-Twin Creeks Project required provisions accommodating underground construction of the Aspen-Golden lines.
Disposition
affirmed
Cases Cited (7)
- BASF Corp. v. State Corp. Comm'n, 289 Va. 375, 391, 394-95, 399-400(followed)
- Office of the Att'y Gen. v. State Corp. Comm'n, 288 Va. 183, 190(followed)
- Appalachian Voices v. State Corp. Comm'n, 277 Va. 509, 516(followed)
- West Virginia v. State Corp. Comm'n, 304 Va. 148, 158, 160, 162-63 (2025)(followed)
- Appalachian Power Co. v. State Corp. Comm'n, 301 Va. 257, 292(followed)
- Board of Supervisors v. Appalachian Power Co., 216 Va. 93, 100, 104-05(followed)
- Piedmont Env't Council v. Virginia Elec. & Power Co., 278 Va. 553, 559, 570 (2009)(followed)
Cited In (0)
No citing cases on record yet.