Hecate Energy LLC v. FERC

126 F.4th 660 (D.C. Cir. 2025) · United States Court of Appeals for the District of Columbia Circuit · January 21, 2025 · No. 23-1089

Summary

This D.C. Circuit opinion addresses whether Hecate Energy LLC has Article III standing to challenge Federal Energy Regulatory Commission orders approving PJM Interconnection’s reforms to its electricity grid interconnection process. The court holds that Hecate lacks standing because its claimed injury—exclusion from an expedited review process for projects costing over $5 million—is not redressable. Vacating the agency’s approval would not likely compel PJM to include Hecate’s project in the expedited track, as PJM retains independent discretion and multiple alternative options to address any regulatory defects. Consequently, the court dismisses the petitions for review without reaching the merits.

Court
United States Court of Appeals for the District of Columbia Circuit
Writing for the Court
HENDERSON; PILLARD; CHILDS
Jurisdiction
United States Court of Appeals for the District of Columbia Circuit
Decision date
January 21, 2025
Docket number
23-1089
Procedural posture
Petition for review of FERC orders approving PJM's interconnection reform package, including a $5 million cap for the Expedited Process.
Standard of review
arbitrary and capricious standard under the Administrative Procedure Act
Precedential value
published
Parties
Hecate Energy LLC v. Federal Energy Regulatory Commission
Disposition
dismissed

Topics

judicial review of agency actionstandard of reviewappellate procedureadministrative law

Practice areas

administrative lawenergy law

Questions Presented

  1. Whether Hecate Energy LLC has Article III standing to challenge FERC's approval of PJM's $5 million cap for the Expedited Process.

Holdings

  1. Hecate lacks Article III standing; the petitions for review are dismissed.

Key quotations

We hold that Hecate lacks Article III standing to challenge the $5 million cap, and therefore dismiss its petitions for review. (at *)

Factual background

Hecate Energy LLC develops renewable power facilities and sought interconnection through PJM. PJM adopted a reform package that created an Expedited Process for projects whose estimated network upgrade costs are $5 million or less. Hecate challenged the $5 million eligibility cap as arbitrary, capricious, and unduly discriminatory.

Procedural history

Hecate intervened in FERC's proceeding, filed a limited protest to the $5 million cap, FERC denied rehearing and approved the reforms; Hecate then petitioned the D.C. Circuit for review.

Court Document

Open PDF
Loading document…