Reliance Steel Products Company v. National Fire Insurance Company of Hartford

880 F.2d 575 (1st Cir. 1989) · United States Court of Appeals for the First Circuit · May 25, 1989 · No. No. 88-1870

Summary

The First Circuit reviewed a bench-trial judgment awarding Reliance Steel Products Company damages against a surety for unpaid construction materials supplied for the Mt. Hope Bridge project. The court upheld the district court’s factual findings regarding project delays and defective materials under the clearly erroneous standard, but held that the calculation of the setoff improperly omitted overhead and profit on riser bar repairs. The court directed entry of a modified judgment for $447,081.54, plus interest and costs.

Court
United States Court of Appeals for the First Circuit
Writing for the Court
Selya, Circuit Judge; Campbell, Chief Judge; Gray, Senior District Judge, sitting by designation
Jurisdiction
Federal
Decision date
May 25, 1989
Docket number
No. 88-1870
Procedural posture
Reliance sued National Fire Insurance Company of Hartford in federal district court under diversity jurisdiction to recover amounts allegedly owed for specialty steel supplied on a bridge renovation project. After a bench trial, the district court entered judgment for Reliance in the net amount of $454,196.10 after setoffs. National Fire appealed, challenging factual findings concerning project delays and the amount of offsets for defective goods.
Standard of review
Findings of fact in a bench trial are reviewed for clear error under Federal Rule of Civil Procedure 52(a). The appellate court deferred to the district court's choice among permissible factual inferences and credibility determinations.
Precedential value
published precedential federal appellate opinion
Parties
National Fire Insurance Company of Hartford v. Reliance Steel Products Company
Disposition
reversed_and_remanded

Topics

construction lawinsurancecontractsstandard of reviewappellate procedure

Practice areas

construction lawinsurancecontractscommercial litigationappellate procedure

Questions Presented

  1. Whether the district court clearly erred in finding that Reliance did not cause or materially contribute to delays in the bridge project.
  2. Whether the district court clearly erred in limiting National Fire's setoffs for losses allegedly caused by defective or misfabricated goods.
  3. Whether the riser-bar repair setoff was incorrectly calculated by omitting applicable overhead and profit.

Holdings

  1. The district court's finding that Reliance did not cause delays warranting an offset was supported by the evidence and was not clearly erroneous.
  2. The appellate court would not disturb the district court's factual findings or limited setoffs where the evidence supported them and the appellant merely reargued the weight and significance of the evidence.
  3. A claimed element of loss must be computed in a rational manner upon a firm factual basis; generalized evidence of labor, equipment, or expense is insufficient without a concrete showing of actual additional loss or diversion.
  4. The district court clearly erred by omitting overhead and profit from the riser-bar repair credit; the credit had to be increased to $41,016.46, producing a total setoff of $60,923.20 and a judgment of $447,081.54 plus interest and costs.

Key quotations

Where there are two permissible views of the evidence, the factfinder's choice between them cannot be clearly erroneous.
a claimed element of loss must be computed in some rational way upon a firm factual base.

Factual background

The Rhode Island Turnpike and Bridge Authority undertook renovation of the Mt. Hope Bridge and awarded the general contract to Dick Corporation, whose payment bond was issued by National Fire. Reliance supplied specialty steel items, but project delays occurred and Reliance was not fully paid. The district court found that Reliance did not cause the delays, while some riser bars and grid panels supplied by Reliance were defective and warranted repair-related setoffs.

Procedural history

The Rhode Island Turnpike and Bridge Authority awarded Dick Corporation a bridge-renovation contract, and National Fire provided a payment bond. Reliance, a material supplier, sued the surety after remaining unpaid. The district court found that Reliance did not cause or materially contribute to project delays, found limited defects in certain riser bars and grid panels, awarded Reliance $508,000.74 less $53,804.64 in setoffs, and entered judgment for $454,196.10. The First Circuit affirmed the factual findings and most of the judgment but held that the riser-bar repair offset had to include applicable overhead and profit, directing entry of judgment for $447,081.54 plus interest and costs.

Remand instructions

Vacate and reenter the judgment to reflect a balance owed by National Fire to Reliance of $447,081.54, plus interest and costs, incorporating a total setoff of $60,923.20. The district court may make any other adjustments necessary in light of the opinion.