Rand Development Corp. v. Sus

3 Mass. Supp. 31 (1981) · Massachusetts Superior Court · November 30, 1981

Summary

The Massachusetts Superior Court considers motions to dismiss and for summary judgment arising from a subcontract for construction of MBTA platform shelters. The court allows the individual defendant’s motion to dismiss an interference-with-contract claim, finding insufficient allegations of malice or actionable interference, but denies the corporate defendant’s motion because the parties disputed whether contractual approval conditions had been satisfied. The decision addresses pleading standards under Massachusetts Rules of Civil Procedure 8(a) and 12(b)(6), and summary judgment under Rule 56.

Court
Massachusetts Superior Court
Writing for the Court
Paul G. Garrity
Jurisdiction
Massachusetts
Decision date
November 30, 1981
Procedural posture
The plaintiff brought claims for interference with contractual rights and breach of contract. Defendant Tamulis moved to dismiss under Mass. R. Civ. P. 12(b)(6), and T Equipment Corp. separately moved under Rule 12(b)(6) based on an alleged unfulfilled contractual approval condition. Because T Equipment Corp. submitted affidavits and documents and the plaintiff submitted opposing materials, the court treated that motion as one for summary judgment under Rule 12(b).
Standard of review
On a Rule 12(b)(6) motion, dismissal is appropriate only if it appears certain that the plaintiff is not entitled to relief under any state of facts that could be proved in support of the claim, with all inferences taken in the plaintiff's favor. When matters outside the pleadings are considered, the motion is treated as one for summary judgment under Rule 56, which requires the absence of a genuine issue as to any material fact and entitlement to judgment as a matter of law.
Precedential value
Published Massachusetts Superior Court decision; persuasive trial-level authority.
Disposition
other

Topics

motions to dismisssummary judgmentintentional interference with contractbreach of contractcivil procedure

Practice areas

civil procedurecontractstortsconstruction lawcommercial litigation

Questions Presented

  1. Whether the complaint stated a claim for interference with contractual relations against Tamulis based on his alleged disregard of the contractual obligations of T Equipment Corp.
  2. Whether Tamulis, as president of T Equipment Corp., was personally liable for interference with the corporation's contract absent allegations of actual malevolence or malice.
  3. Whether T Equipment Corp. was entitled to summary judgment on the ground that the subcontract was conditional and the required approvals had not been obtained.

Holdings

  1. The complaint did not state an actionable interference claim against Tamulis because it alleged that he disregarded the allegedly wrongful acts of others but did not plead that his omission occurred in the face of an explicit affirmative duty to act or allege the required unjustified purpose to cause harm.
  2. Tamulis was not personally liable on the allegations presented because the complaint alleged no actual malevolence or malice in the sense of intentionally causing harm without justification, and corporate officers receive a qualified privilege when acting toward corporate purposes.
  3. T Equipment Corp. was not entitled to summary judgment because the parties disputed whether the required approvals had been obtained, creating a genuine issue of material fact concerning the validity and enforceability of the contract.

Key quotations

A motion to dismiss under Rule. 12(b)(6) should be granted if and only if it appears certain that the plaintiff is not entitled to relief under any state of facts which could be proved in support of the claim and all inferences are to be taken in the plaintiff’s favor. (33)
The parties, vigorously dispute the fulfillment of this condition and therefore the validity of the contract. This is without doubt a genuine issue as to a material fact, and T Equipment Corp. is not entitled to judgment as a matter of law. (34)

Factual background

T Equipment Corp. subcontracted with Rand Development Corporation to construct MBTA platform shelters, and the parties later amended the subcontract to reduce the contract amount. The subcontract and amendment stated that the contract was contingent on approval by Susi and the Massachusetts Department of Public Works. The plaintiff alleged that Tamulis, T Equipment Corp.'s president, disregarded the plaintiff's contractual rights and induced a breach, while T Equipment Corp. asserted that the required approvals had never been received. Affidavits and project documents submitted by the parties suggested conflicting evidence concerning whether the amended subcontract had received the necessary approvals.

Procedural history

The action was before the Massachusetts Superior Court on motions by Tamulis and T Equipment Corp. The court allowed Tamulis's motion to dismiss because the complaint did not adequately allege actionable interference or malice against him. The court denied T Equipment Corp.'s motion because the parties disputed whether the contractual approval condition had been fulfilled, creating a genuine issue of material fact.

Court Document

Open PDF
Loading document…