Trinity Industries, Inc. v. Greenlease Holding Company

Trinity Industries, Inc. v. Greenlease Holding Co., 903 F.3d 333 (3d Cir. 2018) · United States Court of Appeals for the Third Circuit · September 11, 2018 · No. Nos. 16-1994 & 16-2244

Summary

The Third Circuit held that contractual indemnification provisions with a three-year term did not bar subsequent CERCLA contribution claims where the agreement contained non-assumption of liabilities and non-waiver of remedies clauses preserving statutory rights. The court affirmed that response costs incurred under a state consent decree were necessary and reasonable under CERCLA, but vacated the district court's 62% cost allocation because the court improperly used a volumetric methodology that failed to differentiate between remediation activities with varying costs and erroneously equated square footage with cubic yardage. The court also found error in equitable deductions for indemnification intent (lacking mutual intent) and property value increase (no record evidence), and affirmed that a parent corporation was not directly or derivatively liable for its subsidiary's contamination where the subsidiary maintained day-to-day operational control.

Court
United States Court of Appeals for the Third Circuit
Writing for the Court
Jordan; Chagares; Hardiman
Jurisdiction
Federal
Decision date
September 11, 2018
Docket number
Nos. 16-1994 & 16-2244
Procedural posture
Cross-appeals from the United States District Court for the Western District of Pennsylvania's allocation of cleanup costs under CERCLA and HSCA.
Standard of review
De novo for legal issues, clear error for factual findings, abuse of discretion for equitable allocation.
Precedential value
Published
Parties
Trinity Industries, Inc., Trinity Industries Railcar Corporation, Greenlease Holding Company v. Trinity Industries, Inc., Trinity Industries Railcar Corporation, Ampco-Pittsburgh Corporation
Disposition
remanded

Topics

civil procedureappellate procedurestandard of reviewsummary judgmentcontractscorporate lawindemnityremediescommercial litigation

Practice areas

Environmental LawContributionCERCLA

Questions Presented

  1. Whether the indemnification provisions bar contribution under CERCLA and HSCA.
  2. Whether the costs Trinity incurred were necessary and reasonable under CERCLA.
  3. Whether the District Court's cost allocation methodology was proper.
  4. Whether the equitable deductions of 5% and 10% were proper.
  5. Whether Ampco is directly or derivatively liable for Greenlease's share of cleanup costs.

Holdings

  1. The indemnification provisions do not preclude Trinity from seeking contribution because the Agreement's non-assumption of liabilities and non-waiver of remedies clauses preserved Trinity's statutory rights.
  2. The costs were necessary and reasonable because they had a nexus to the environmental cleanup and were incurred in compliance with the consent decree.
  3. The District Court abused its discretion by using a speculative methodology that failed to differentiate between remediation activities and treated different units of measurement as equivalent.
  4. The District Court abused its discretion because the 5% deduction was based on a misapplication of Beazer East (no mutual intent to shift liability), and the 10% deduction had no evidentiary support regarding property value.
  5. Ampco is not directly liable as an operator because it did not manage day-to-day operations of the North Plant, and not derivatively liable because the evidence does not support piercing the corporate veil.

Key quotations

The whole instrument must be taken together in arriving at contractual intent. (21)
We will not construe the indemnification provision to cover time periods that, by the plain language of the contract, it does not cover. (22-23)
A cost is considered 'necessary' and hence subject to shared liability if there is 'some nexus between [it] and an actual effort to respond to environmental contamination.' (27)
We clarify here that such a volumetric-centered approach is only appropriate where the evidence supports a finding that one standardized volumetric unit correlates with a standardized per unit measure of cost. (39)
It is only appropriate to take increased value into consideration when there is evidence concerning an actual increase, such as proof of the fair market value of the property before and after the cleanup. (48)

Factual background

The North Plant in Greenville, Pennsylvania was used for railcar manufacturing from 1910. Greenlease owned the site from 1910 to 1986, using lead paint and chemicals. Trinity acquired the site in 1986 and operated until 2000. Pennsylvania investigated and Trinity entered a consent decree to remediate, costing nearly $9 million. Trinity sought contribution from Greenlease and Ampco.

Procedural history

Trinity filed suit against Greenlease and Ampco in 2008. The District Court granted partial summary judgment, held a bench trial, and allocated 62% of costs to Greenlease. Both parties appealed.

Remand instructions

On remand, the District Court should adhere to a cost allocation methodology that differentiates between major remediation activities and accounts for varying costs, and may reopen the record to receive additional evidence. The court should also reconsider the equitable deductions consistent with the opinion.

Court Document

Open PDF
Loading document…