Alacrity Solutions Group, LLC v. Triage Restoration

Alacrity Solutions Group · United States District Court for the District of Oregon · July 24, 2025 · No. 6:23-cv-01617-MTK

Summary

This United States District Court opinion grants the plaintiff's motion for summary judgment in a breach of contract dispute involving a third-party construction contractor administrator and a general contractor. The court determined that the Network Membership Agreement unambiguously mandated reimbursement for completed work rather than upfront funding, finding that the defendant breached the contract by abandoning the project when refused advance payments. While liability and the duty to reimburse direct costs were established, the court denied summary judgment on the indemnity claim regarding third-party claims due to insufficient evidence linking those damages exclusively to the defendant's breach.

Court
United States District Court for the District of Oregon
Writing for the Court
Mustafa T. Kasubhai
Jurisdiction
United States District Court for the District of Oregon
Decision date
July 24, 2025
Docket number
6:23-cv-01617-MTK
Procedural posture
Plaintiff moved for summary judgment on liability for breach of contract and indemnification arising from a construction-restoration assignment. The court granted the motion in part and denied it in part.
Standard of review
Under Federal Rule of Civil Procedure 56(a), summary judgment is proper when the record shows no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law. Materiality is determined by substantive law, and a dispute is genuine when the evidence could permit a reasonable jury to return a verdict for the nonmoving party. Reasonable doubts and factual inferences are construed in favor of the nonmoving party.
Precedential value
unpublished federal district court opinion; precedential status unknown
Disposition
other

Topics

breach of contractcontract interpretationindemnitywaiver of breachsummary judgment

Practice areas

contractscommercial litigationconstruction lawcivil procedure

Questions Presented

  1. Whether the Network Membership Agreement was unambiguous concerning the timing and availability of interim payments.
  2. Whether Triage breached the agreement by failing to timely start and complete the Benefield Assignment without advance funding.
  3. Whether Alacrity waived its contractual right to require work before releasing interim funds.
  4. Whether Triage breached the agreement by failing to reimburse Alacrity for costs incurred after Triage's default.
  5. Whether the agreement's indemnity clause applies to direct claims between Alacrity and Triage or only to qualifying third-party claims.
  6. Whether summary judgment was proper on alleged damage to adjoining property and additional living expenses.
  7. Whether Alacrity was entitled to prevailing-party attorney fees.

Holdings

  1. The Network Membership Agreement and PAS Addendum are unambiguous: absent an agreement for different payment terms, progress payments are discretionary and are issued for work the contractor has already performed.
  2. Triage breached the Network Membership Agreement by failing to timely start and by refusing to complete the Benefield Assignment without advance funding.
  3. Alacrity did not waive its contractual right to require performance before releasing interim funds.
  4. Triage breached the NMA by refusing to reimburse Alacrity for costs incurred because of Triage's default after Alacrity reassigned and completed the project.
  5. Summary judgment was improper on whether Triage caused water and mold damage to the adjoining property because causation remained disputed.
  6. The NMA's indemnity clause does not apply to direct, first-party claims between Alacrity and Triage; it applies to qualifying third-party claims or proceedings involving Triage's conduct.
  7. Alacrity was not entitled to summary judgment on indemnity-related damages because it failed to establish that Triage was the cause of the claimed third-party losses.
  8. Alacrity was entitled to reasonable prevailing-party attorney fees on the claims for which it obtained a favorable judgment, although the amount of damages remained unresolved.

Key quotations

The Court finds that the contract did not require Plaintiff to provide upfront funding and Defendant breached the contract when it abandoned the project. (Background)
Unless agreed to otherwise, progress payments are issued at Plaintiff’s discretion and for work that the Contractor has already performed. (Discussion, Part I.A.1)
The Court finds that the indemnity clause of the NMA does not apply to direct claims between Plaintiff and Defendant. (Discussion, Part II)
For the reasons above, Plaintiff’s Motion for Summary Judgment (ECF No. 22) is GRANTED in part and DENIED in part. (Conclusion)

Factual background

Alacrity administered a network of construction contractors and entered into a Network Membership Agreement with Triage Restoration after Alacrity and Nexxus merged. The agreement provided that interim payments were discretionary and generally would be disbursed for work already performed, rather than requiring Alacrity to fund work upfront. After accepting the Benefield Assignment, Triage repeatedly stated that it could not carry project costs without advance funding and ultimately offered to release the homeowner from the contract; Alacrity reassigned the project to another contractor. Alacrity also alleged that Triage caused damage to an adjoining property and that Triage's abandonment caused additional living expenses, but the court found causation for those losses disputed or inadequately supported.

Procedural history

Alacrity Solutions Group sued Triage Restoration in federal district court after Triage stopped working on a property-restoration assignment and allegedly refused to continue without advance funding. Alacrity moved for summary judgment. The court held that Triage breached the Network Membership Agreement by failing to timely start and complete the assignment and by refusing to reimburse certain default-related costs, but found factual disputes concerning damage to adjoining property and the causation of additional living expenses. The court also denied summary judgment on the indemnity-related damages while awarding Alacrity prevailing-party attorney fees.

Court Document

Open PDF
Loading document…