Duquesne Light Co. v. Barasch

488 U.S. 299 (1989) · Supreme Court of the United States · January 11, 1989 · No. No. 87-1160

Summary

The United States Supreme Court held that Pennsylvania's utility-rate regulation scheme did not violate the Takings Clause by disallowing recovery of prudently incurred costs for nuclear generating plants that were never built. The Court reaffirmed that the constitutionality of utility rates depends on the overall effect of the rate order rather than adherence to a particular ratemaking methodology. The judgment of the Supreme Court of Pennsylvania was affirmed.

Court
Supreme Court of the United States
Writing for the Court
Chief Justice Rehnquist; Justice Blackmun; Justice White; Justice Marshall; Justice Stevens; Justice O'Connor; Justice Scalia; Justice Kennedy; Justice Souter
Jurisdiction
Federal
Decision date
January 11, 1989
Docket number
No. 87-1160
Procedural posture
The utility companies appealed the judgment of the Supreme Court of Pennsylvania, which interpreted Pennsylvania's utility statute to prohibit recovery through rates of prudently incurred costs associated with canceled generating plants and rejected the utilities' Takings Clause challenge.
Standard of review
De novo review of the federal constitutional issue and appellate-jurisdiction question.
Precedential value
binding
Parties
Duquesne Light Co., Pennsylvania Power Co. v. David M. Barasch, Pennsylvania Public Utility Commission
Disposition
affirmed

Topics

takings clauseconstitutional lawappellate jurisdictionfinal judgment ruleadministrative law

Practice areas

constitutional lawutility regulationadministrative lawappellate jurisdiction

Questions Presented

  1. Whether the Supreme Court of Pennsylvania's judgment was final for purposes of the Supreme Court's appellate jurisdiction under 28 U.S.C. § 1257(2), despite remand for further state-court proceedings.
  2. Whether Pennsylvania Act 335 violated the Fifth Amendment Takings Clause, as applied to the States through the Fourteenth Amendment, by preventing electric utilities from recovering prudently incurred capital costs for generating facilities that were canceled before being used and useful in public service.
  3. Whether the Constitution requires utility rates to be established under a particular ratemaking methodology, such as the fair-value or prudent-investment rule.

Holdings

  1. A state-court judgment is final under 28 U.S.C. § 1257(2) when the highest state court has finally adjudicated the federal constitutional issue and further proceedings are effectively preordained, even though the case has been remanded for implementation.
  2. A state utility-regulation scheme does not take property merely because it disallows recovery of capital investments that are not used and useful in service to the public.
  3. The Constitution does not require the use of any single ratemaking methodology, including the fair-value or prudent-investment rule.

Key quotations

a state scheme of utility regulation does not "take" property simply because it disallows recovery of capital investments that are not "used and useful in service to the public." (488 U.S. at 301-302)
it is not theory but the impact of the rate order which counts. (488 U.S. at 310)
The Constitution within broad limits leaves the States free to decide what ratesetting methodology best meets their needs in balancing the interests of the utility and the public. (488 U.S. at 316)

Factual background

Duquesne Light Company and Pennsylvania Power Company invested in the CAPCO project to construct seven nuclear generating units. In 1980, plans for four units were canceled after economic and energy-market conditions changed, leaving the utilities with substantial preliminary construction costs that had been prudently incurred. The Pennsylvania Public Utility Commission initially permitted amortized recovery of those costs, but Pennsylvania Act 335 barred their inclusion in rates because the facilities were not used and useful in service to the public.

Procedural history

The Pennsylvania Public Utility Commission initially allowed Duquesne Light and Pennsylvania Power to amortize costs incurred for canceled nuclear generating units. The Commonwealth Court affirmed the Commission's statutory interpretation. The Supreme Court of Pennsylvania reversed, held that the statute prohibited recovery of the costs by either rate-base inclusion or amortization, rejected the constitutional challenge, and remanded to the Commission to revise the rate orders. The United States Supreme Court noted probable jurisdiction, held that the state-court judgment was final for purposes of appellate jurisdiction, and affirmed.

Remand instructions

The Pennsylvania Public Utility Commission was to revise the relevant rate orders to exclude recovery of the canceled CAPCO generating-plant costs as required by Act 335.

Court Document

Open PDF
Loading document…