Summary
This corrected post-trial decision resolves a contract dispute between Eastern States Construction Service, Inc. and several Capano-affiliated development entities concerning heavy civil site-development projects. The court found that both sides breached their contracts, offset their respective damages, and awarded the Developers $50,189.25. The court declined to award attorneys’ fees to either party.
Holdings
- The pay-when-paid provision established the timing of payment and did not make receipt of third-party funding a condition precedent to Developers' obligation to pay Eastern States.
- The holdback provision did not permanently excuse Developers' obligation to pay Eastern States for work performed.
- The contracts did not make time of the essence, and the court would not insert an unwritten time-is-of-the-essence term.
- Developers did not invoke the notice provision and therefore did not timely dispute Eastern States' payment applications under the contracts.
- Developers materially breached the contracts by failing to pay Eastern States' submitted invoices.
- Eastern States breached the contracts by performing defective work and failing to comply with DelDOT requirements, and Developers could recover damages for that defective work.
- Developers' continued performance and repeated inducement of Eastern States' work after learning of alleged breaches waived any right to treat those breaches as discharging their obligation to pay for work already performed.
- Developers could recover costs attributable to repairing Eastern States' defective work, but could not recover costs to finish work that Developers prevented Eastern States from completing by terminating it without the contractual written notice.
- Eastern States was not entitled to lost profits because its proof was conjectural and speculative.
- Eastern States' unjust-enrichment claim was dismissed because the parties' relationship was comprehensively governed by valid and enforceable contracts.
- Developers' express- and implied-warranty claims were dismissed as duplicative of their breach-of-contract claims.
- Developers' declaratory-judgment claim was dismissed as duplicative of the breach-of-contract claims and, insofar as it concerned future conduct, was unripe.
- Neither party was awarded attorneys' fees.
Questions Presented
- Whether Developers breached the contracts by failing to pay Eastern States' submitted invoices.
- Whether the pay-when-paid provision made receipt of third-party funding a condition precedent to Developers' payment obligation.
- Whether the holdback provision excused Developers' nonpayment.
- Whether the contracts made time of the essence and whether Eastern States' delays constituted material breaches.
- Whether Developers' failure to invoke the contractual notice provision barred them from disputing Eastern States' payment applications.
- Whether Developers elected to continue the contracts after learning of Eastern States' alleged breaches, thereby preserving their obligation to pay for work performed.
- Whether Eastern States breached the contracts by performing defective work and failing to comply with DelDOT requirements.
- Whether Developers could recover costs to complete work after terminating Eastern States.
- Whether Eastern States was entitled to lost profits.
- Whether Eastern States could recover under unjust enrichment despite the governing contracts.
- Whether Developers' warranty and declaratory-judgment counterclaims were duplicative of their breach-of-contract claims.
- Whether either party was entitled to attorneys' fees.
Disposition
other
Cases Cited (41)
- Navient Solutions, LLC v. BPG Office Partners XIII Iron Hill LLC, 2023 WL 3120644 (Del. Super. Ct. Apr. 27, 2023)(followed)
- Feenix Payment Systems, LLC v. Blum, 2024 WL 2768386 (Del. Super. Ct. May 29, 2024)(followed)
- Interim Healthcare, Inc. v. Spherion Corp., 884 A.2d 513 (Del. Super. Ct. 2005)(followed)
- Torres v. Bishop, 2021 WL 6053870 (Del. Super. Ct. Dec. 21, 2021)(followed)
- Pencader Associates, LLC v. Synergy Direct Mortgage Inc., 2010 WL 2681862 (Del. Super. Ct. June 30, 2010)(followed)
- Mundy v. Devon, 906 A.2d 750 (Del. 2006)(followed)
- Pardo v. State, 160 A.3d 1136 (Del. 2017)(followed)
- Active Day OH, Inc. v. Wehr, 2024 WL 3201167 (Del. Super. Ct. June 27, 2024)(followed)
- Zenith Energy Terminals Joliet Holdings LLC v. CenterPoint Properties Trust, 2023 WL 615997 (Del. Super. Ct. Jan. 23, 2023)(followed)
- Lorillard Tobacco Co. v. American Legacy Foundation, 903 A.2d 728 (Del. 2006)(followed)
Showing top 10 of 41.
Cited In (0)
No citing cases on record yet.
Court Document
Open PDFLoading document…