Herrmann v. Wolf Point School District

84 P.3d 20 (Mont. 2004); 2004 MT 10 · Supreme Court of Montana · January 27, 2004 · No. No. 01-559

Summary

The Supreme Court of Montana held that the district court had subject matter jurisdiction over workers’ negligence and breach of contract claims against a school district arising from the failure to include Davis-Bacon prevailing-wage provisions in federally funded construction contracts. Because the contracts did not incorporate the Davis-Bacon Act and there was no federal contracting party, the workers lacked federal administrative or Miller Act remedies and could pursue state-law claims. The court reversed the dismissal and remanded for further proceedings.

Court
Supreme Court of Montana
Writing for the Court
Patricia O. Cotter; Karla M. Gray; James C. Nelson; W. William Leaphart; Jim Regnier; Jim Rice
Jurisdiction
Montana
Decision date
January 27, 2004
Docket number
No. 01-559
Procedural posture
Plaintiffs appealed the dismissal of their negligence and breach-of-contract complaint under Rule 12, M.R.Civ.P., for lack of subject matter jurisdiction and related grounds.
Standard of review
A motion to dismiss should not be granted unless it appears beyond doubt that the plaintiff can prove no set of facts entitling the plaintiff to relief. The complaint is construed in the light most favorable to the plaintiff and its factual allegations are taken as true. Subject matter jurisdiction is reviewed as a conclusion of law, and conclusions of law are reviewed for correctness.
Precedential value
published precedential opinion
Parties
LaMoyne Herrmann, Sherman Talks Different v. Wolf Point School District
Disposition
reversed_and_remanded

Topics

motions to dismisssubject matter jurisdictionnegligencebreach of contractappellate procedure

Practice areas

civil proceduretortscontractsconstruction lawgovernment contractsappellate procedure

Questions Presented

  1. Whether the district court had subject matter jurisdiction over the plaintiffs' state-law negligence and breach-of-contract claims arising from the School District's failure to include Davis-Bacon prevailing-wage provisions in the project documents.
  2. Whether the complaint adequately stated claims that could survive a motion to dismiss.

Holdings

  1. The district court incorrectly concluded that it lacked subject matter jurisdiction over the Workers' complaint. Because the construction contracts contained no Davis-Bacon provision and no federal contracting party was involved, the Workers had no available Davis-Bacon administrative or Miller Act remedy and could pursue their asserted state-law claims in state court.
  2. The allegations in the complaint were sufficient to survive the School District's motion to dismiss and to vest the district court with subject matter jurisdiction over the Workers' negligence and breach-of-contract action.

Key quotations

Motions to dismiss should not be granted unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief. (¶ 9)
We hold that the District Court incorrectly concluded that it lacked subject matter jurisdiction over the Workers' Complaint. Therefore, we reverse and remand to allow the Workers to proceed with their negligence and breach of contract action against the WPSD. (¶ 22)

Factual background

The Wolf Point School District undertook a high school addition on the Fort Peck Indian Reservation using District funds and predominantly federal Impact Aid funds. The District hired a principal contractor and architect, and the plaintiffs worked for a subcontractor on the project. Although the District was contractually obligated under its federal funding agreement to ensure that Davis-Bacon wage provisions were included in construction contracts, those provisions were not included, and the plaintiffs alleged that they consequently were not paid prevailing wages and lacked a Davis-Bacon remedy.

Procedural history

Workers employed by a subcontractor on a federally funded school construction project sued the Wolf Point School District, alleging that it negligently and contractually failed to require payment of Davis-Bacon prevailing wages in the project documents. The Fifteenth Judicial District Court dismissed the complaint, concluding that the plaintiffs lacked a private state cause of action based on the Davis-Bacon Act, that negligence per se and common-law negligence claims could not proceed, and without addressing the breach-of-contract claim. The Montana Supreme Court reversed and remanded.

Remand instructions

The district court was directed to allow the Workers to proceed with their negligence and breach-of-contract action and to develop the record regarding the funding contract, the School District's contractual obligations, breach, and negligence.

Court Document

Open PDF
Loading document…